162913918 | 5 months ago | I have already done so. The vicroads database supports the name being Old Geelong Road. |
162913918 | 5 months ago | Official sources say the name is 'Old Geelong Road' until the intersection with Rowland Road. This is incorrect. |
162913197 | 5 months ago | This is incorrect - The masterplan for the Werribee Township Regional Park (the area where the road goes through) is not yet complete, and even then it is unlikely that the road will be extended in this way. |
162991710 | 5 months ago | This section of road will likely be upgraded in the future once it is extended, but I don't see that happening within the next couple years. |
162989491 | 5 months ago | One of my extended family members owns the large block of land north of Woodbury estate, and I am pretty sure it hasn't even been sold yet, let alone subdivided and planned. The extension of Forsyth Road is unlikely to happen until at least a year or so after they sell it anyways. |
161450335 | 7 months ago | I've removed the parking space you added in this edit as there is no evidence this area is actually used for parking. The masterplan at https://westernmelbournegroup.com/residential/ indicates this area will be residential. |
160700195 | 7 months ago | Werribee, Frankston, and Mornington are suburbs and not separate towns/cities from Melbourne and should not be tagged as such. Also, you used population data from the Local Government Area of Frankston instead of the suburb of Frankston. These changes have been reverted. Please let me know if you have any questions. |
157921868 | 8 months ago | I honestly don't remember, this changeset was 2 months ago. Feel free to re-tag them. |
157921868 | 8 months ago | my apologies, i thought you were mentioning roads under construction, sorry. |
157921868 | 8 months ago | Feel free to let me know if you have any other questions. |
157921868 | 8 months ago | Hello, thank you for your message. These roads are part of Vicmap's road database, and indicate roads that have been declared and are to be built. While those roads may not have been started physically yet, preparation is certainly underway for them and they should be completed over the next few months. |
157852084 | 10 months ago | You have tagged the entire school as a single building under construction, which is incongruent with the school's plan, and does not make sense overall. Further, the school was completed in Q1 2024, so there is no need to add under construction buildings. |
157832494 | 10 months ago | Thank you for reminding me. I seem to have done this correctly in older mapping, no idea why I've forgotten. |
155908018 | 11 months ago | I have reverted these changesets as they are completely inaccurate, with no reason provided as to why they were made. |
155761585 | 11 months ago | I have reverted these changesets as they are completely inaccurate, with no reason provided as to why they were made. |
155583192 | 11 months ago | I have reverted these changesets as they are completely inaccurate, with no reason provided as to why they were made. |
155582932 | 11 months ago | I have reverted these changesets as they are completely inaccurate, with no reason provided as to why they were made. |
155582832 | 11 months ago | I have reverted these changesets as they are completely inaccurate, with no reason provided as to why they were made. |
155582815 | 11 months ago | I have reverted these changesets as they are completely inaccurate, with no reason provided as to why they were made. |